CompTIA PK0-005 Practice Test

Prepare smarter and boost your chances of success with our CompTIA PK0-005 Practice test. This test helps you assess your knowledge, pinpoint strengths, and target areas for improvement. Surveys and user data from multiple platforms show that individuals who use PK0-005 practice exam are 40–50% more likely to pass on their first attempt.

Start practicing today and take the fast track to becoming CompTIA PK0-005 certified.

13610 already prepared
Updated On : 30-Jun-2025
361 Questions
4.8/5.0

Page 6 out of 37 Pages

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

A. Performing

B. Adjourning

C. Forming

D. Norming


D.   Norming

Explanation: The current stage of the project team is norming, which is the third stage of the five stages of team development. In this stage, the team members have resolved their conflicts and differences, and have established a sense of cohesion and collaboration. They are more productive, supportive, and cooperative, and they follow the agreed norms and rules of the team. They also communicate effectively and seek feedback and assistance from each other. The norming stage is preceded by the forming stage, where the team members get to know each other and the project goals, and the storming stage, where the team members experience disagreements and challenges. The norming stage is followed by the performing stage, where the team members work efficiently and autonomously towards the project outcomes, and the adjourning stage, where the team members complete the project and celebrate their achievements.

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

A. Escalate the change to the CCB.

B. Review the requested change.

C. Document the change recommendations.

D. Validate the implementation of the requested change.


B.   Review the requested change.

Explanation: The project manager should review the requested change first to assess its impact, feasibility, and alignment with the project objectives and scope. Reviewing the change will help the project manager to determine if the change is necessary, beneficial, and acceptable to the stakeholders. The project manager should also consider the risks, costs, and quality implications of the change before proceeding to the next steps of the change management process123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; 5 Steps in the Change Management Process | HBS Online; 8 Steps for an Effective Change Management Process - Smartsheet

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

A. Encryption

B. Multifactor authentication

C. Quality assurance

D. Password protection


A.   Encryption

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

A. Social engineering

B. Phishing

C. Spoofing

D. Hacking


B.   Phishing

Explanation: Phishing is a scenario where someone claiming to be from a legitimate organization sends an email or other message to a target person asking for sensitive information or access to a system or account. Phishing is a type of cyberattack that aims to trick the target into revealing personal or financial data or installing malware on their device. Phishing can compromise the security and privacy of the target and expose them to identity theft, fraud, or other malicious activities.

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

A. Exploit the risk.

B. Accept the risk.

C. Avoid the risk.

D. Transfer the risk.


A.   Exploit the risk.

Explanation: The project manager should exploit the risk after an opportunity emerged in the middle of a project life cycle. Exploit is a risk response strategy that aims to increase the probability and/or impact of a positive risk or opportunity. Exploit can involve actions such as allocating more resources, changing the scope or schedule, or adding more features or benefits to the project deliverables. Exploit can help to ensure that the opportunity is realized and that the project gains more value or advantage from it3

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

A. Regression testing

B. Smoke testing

C. Stress testing

D. Automation testing


C.   Stress testing

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

A. Time and materials contract

B. Master service agreement

C. Fixed-price contract

D. Statement of work

E. Cost-plus agreement


A.   Time and materials contract

Explanation: The project manager should put in place a time and materials contract before work begins for a third party that needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. A time and materials contract is a type of contract where the buyer pays the seller based on the actual time spent and materials used during the project. A time and materials contract is suitable for projects that have uncertain or variable scope, duration, or cost. A time and materials contract can provide flexibility and adaptability for both parties and allow them to adjust to changing requirements or circumstances.

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

A. Key stakeholder identification

B. Preliminary procurement

C. Solution design determination

D. Critical factor enlistment


B.   Preliminary procurement

Which of the following provides the best justification for undertaking a project?

A. Scope statement

B. Business case

C. Sponsor request

D. Project charter


B.   Business case

Which of the following is a consideration when determining a project's ESG factors?

A. Project management methodology

B. IT infrastructure security

C. Proper accounting practices

D. Corporate values compliance


D.   Corporate values compliance

Explanation: Corporate values compliance is a consideration when determining a project’s ESG factors, because it reflects how a project aligns with the ethical standards and social responsibility of the organization. Corporate values compliance can help to enhance the reputation, trust, and loyalty of the organization among its stakeholders, as well as to avoid legal or regulatory issues that may arise from violating the values. Corporate values compliance can also influence the project scope, objectives, deliverables, and stakeholders, as well as the project management methodology, processes, and practices. The other options are not directly related to ESG factors. Project management methodology is the approach or framework that guides how a project is planned, executed, monitored, and controlled. IT infrastructure security is the protection of the hardware, software, network, and data components of a project from unauthorized access, use, modification, or destruction. Proper accounting practices are the rules and standards that govern how financial transactions and statements are recorded, reported, and audited for a project.

Page 6 out of 37 Pages
PK0-005 Practice Test Previous