During a steering committee meeting, members of the meeting decide to implement several proposed suggestions. Which of the following documents should be updated first as a result of this decision?
The change log should be updated first because the steering committee has decided to implement proposed suggestions, which means approved or pending changes must be formally recorded. A change log provides traceability for change requests, approvals, impacts, implementation status, owners, and dates. Updating it first ensures the project has an auditable record before related project documents are revised. The Gantt chart may need updates later if the changes affect schedule activities or milestones. The task board may also be revised if team work items change. The risk log is used for uncertain future events, not approved scope or execution changes. Proper change documentation supports governance, prevents confusion, and helps stakeholders understand why the project plan, schedule, budget, or scope may be adjusted.