Prepare smarter and boost your chances of success with our CompTIA PK0-005 Practice test. This test helps you assess your knowledge, pinpoint strengths, and target areas for improvement. Surveys and user data from multiple platforms show that individuals who use PK0-005 practice exam are 40–50% more likely to pass on their first attempt.
Start practicing today and take the fast track to becoming CompTIA PK0-005 certified.
13610 already prepared
Updated On : 30-Jun-2025361 Questions
4.8/5.0
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
A. Inform the CCB to stop communication
B. Establish a RACI matrix
C. Escalate the communication issues
D. Revise the communication plan
Explanation: When stakeholders express concerns about the volume of communication, it’s important to review and adjust the communication plan to ensure it meets the project’s needs and stakeholders’ preferences. A RACI matrix is useful for defining roles and responsibilities but does not address communication frequency or methods directly. Escalating the issue may not be necessary if it can be resolved by revising the plan. Informing the CCB (Change Control Board) to stop communication is not advisable as the CCB’s role is to oversee changes, not to manage day-to-day communications.
A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?
A. CMS
B. CRM
C. EDRMS
D. ERP
Explanation: ERP (Enterprise Resource Planning) systems are designed to integrate and manage all core functions of a business, such as finance, HR, and supply chain management. This aligns with CompTIA Project+ guidelines on selecting appropriate systems for organizational needs.
A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?
A. Scatter diagram
B. Decision tree
C. Pareto chart
D. Histogram
Explanation: A decision tree helps in evaluating various choices and their potential outcomes, making it suitable for comparing vendors based on costs and risks. This aligns with CompTIA Project+ methodologies for decision-making tools and analysis.
Which of the following is a quality assurance tool?
A. Defining project goals
B. Identifying the root cause analysis
C. Assessing employee efficiency
D. Assessing skill gaps
Explanation: Identifying the root cause analysis. Identifying the root cause analysis is a quality assurance tool that can help to find and eliminate the underlying causes of quality problems or defects. Root cause analysis is a systematic process of asking why a problem occurred and tracing it back to its source. Root cause analysis can help to prevent recurrence of the same or similar problems, improve quality performance, and reduce costs and risks12
Which of the following best represents the project impact to a company's brand value?
A. The project is compliant with local and state laws and becomes the standard for new projects.
B. The project promotes new initiatives to expand its benefit to other communities
C. The project exceeds the sales quota for the third quarter and raises the bar for next periods.
D. The project meets the expected milestones and finishes on time and within budget.
Explanation: the brand of a project should deliver the message about its value and goals, and a proper brand helps the project get the necessary support and increases loyalty. The project that promotes new initiatives to expand its benefit to other communities is the one that best represents the project impact to a company’s brand value, as it shows the company’s vision, cause, and reputation.
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
A. Dashboard
B. Gantt chart
C. Work breakdown structure
D. Requirements Traceability Matrix
Explanation: A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.
During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?
A. Waterfall method
B. Simulation method
C. Precedence diagramming method
D. Cost ratio analysis
Explanation: The Precedence Diagramming Method (PDM) is used to visually represent tasks, dependencies, and sequencing in a project schedule. This technique is consistent with CompTIA Project+ guidelines for planning and managing project timelines.
A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?
A. The retrospective session feedback was not communicated properly.
B. The project resources were released ahead of time.
C. The documentation was not archived as per the PMO standards.
D. The validation of deliverables is running behind schedule.
Explanation: Archiving project documentation is an important process to ensure that the project information is stored, retrieved, and updated in a consistent and efficient
manner1. It also helps to meet legal requirements, enable long-term analysis, and support new projects and team members1. If the documentation was not archived as per the PMO standards, it would be difficult for the current project manager to find the relevant documents and learn from the previous project. This would cause the current project manager to keep asking questions to the previous project manager, who may not have all the answers or may not be available. Therefore, the most likely cause of this situation is that the documentation was not archived as per the PMO
standards. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 14: Closing the Project, page 403; How to Archive a Completed Project: A Guide for PMOs, Introduction and Benefits sections.
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
A. Allocate resources
B. Determine the project budget
C. Develop a communication plan.
D. Establish baselines
Explanation: The next step after defining tasks, durations, resources, and costs is to establish baselines. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Establishing baselines involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution34
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
A. Gantt chart
B. Maintenance window schedule
C. Functional requirements
D. Test results
Explanation: The project manager should consult a Gantt chart after the sponsor states that the project is taking too long to complete. A Gantt chart is a graphical tool that shows the schedule of a project, including the start and end dates, durations, dependencies, milestones, and progress of each task or activity. A Gantt chart can help to monitor and control the project timeline and identify any delays, variances, or issues that may affect the project completion.